Charlotte County East Port Water Reclamation Facility Expansion

Jones Edmunds prepared a preliminary engineering report and provided final design and construction administration services for a phased expansion of the 6-MGD East Port WRF to 9 MGD. Jones Edmunds provided the following services:

  • Capacity assessment of existing unit processes
  • Treatment and hydraulic evaluations required for 9-MGD Annual Average Daily Flow and 27-MGD peak hourly flow
  • Energy conservation evaluation to reduce power and O&M costs
  • Recommended phased expansion program to provide improvements and capacity as needed and meet available funding

Jones Edmunds helped the County procure grant funding (50% matching funds) from the Southwest Florida Water Management District for the reclaimed water plant improvements.

Charlotte County East Port Water Reclamation Facility Expansion

Jones Edmunds prepared a preliminary engineering report and provided final design and construction administration services for a phased expansion of the 6-MGD East Port WRF to 9 MGD. Jones Edmunds provided the following services:

  • Capacity assessment of existing unit processes
  • Treatment and hydraulic evaluations required for 9-MGD Annual Average Daily Flow and 27-MGD peak hourly flow
  • Energy conservation evaluation to reduce power and O&M costs
  • Recommended phased expansion program to provide improvements and capacity as needed and meet available funding

Jones Edmunds helped the County procure grant funding (50% matching funds) from the Southwest Florida Water Management District for the reclaimed water plant improvements.